Public Works Construction Inspectors oversee the construction of streets, alleys, water mains, sanitary sewer mains, drainage systems and city-owned facilities. This page provides information about current construction projects that are in progress or future development. All construction start dates are estimated.
| Pioneer Road Paving and Drainage Improvements |
Reconstruction of Pioneer Road from Belt Line Road to E. Cartwright Road from a 2-lane asphalt section to a 4-lane concrete section with major upgrades to drainage, water and sanitary sewer mains. Project is a joint venture with Dallas County Public Works.
Start Date: Future Development
Estimated Cost: $15,000,000
|
| Paddy Heights Addition Paving Rehabilitation |
Reconstruction of Freeman Street and Kedy Street in the Paddy Heights Addition No. 1.
Start Date: April 2010 (150 Construction Calendar Days)
Estimated Cost: $593,000
|
| Northridge Addition Sanitary Sewer Rehabilitation, Multiple Phases |
Rehabilitation and replacement of sanitary sewer mains in the Northridge Addition Subdivision.
Start Date: Ongoing
Estimated Cost: $9,000,000
|
| Mesquite Hike and Bike Trail, Phase 1 |
Construction of a 4.4 mile illuminated concrete trail for the first section of the City’s main hike and bike trail to connect to the Regional Veloweb in Garland. Project is a joint venture with the Texas Department of Transportation, City of Garland and North Central Texas Council of Governments.
Start Date: Future Development
Estimated Cost: $3,000,000
|
| Faithon P. Lucas Blvd. Roadway Improvements |
Reconstruction of Faithon P. Lucas Boulevard from Cartwright Road to McKenzie Road from existing 2-lanes asphalt to 4-lanes concrete pavement with 6 foot wide bicycle lanes. Project is a joint venture with the Dallas County Public Works.
Start Date: Future Development
Estimated Cost: $12,300,000
|
| Forney Road Paving, Drainage, Water and Sanitary Sewer Improvements |
Reconstruction of the existing 4-lanes on Forney Road from Town East Blvd. to UPRR Intermodal Facility along with the replacement of water mains, sanitary sewer mains and storm drain improvements.
Start Date: March 2010 (300 Construction Calendar Days)
Estimated Cost: $2,000,000
|
| Edgemont Park Addition Water Main Replacement Program, Multiple Phases |
Replacement of older water mains throughout the Edgemont Park Addition Subdivision.
Start Date: Ongoing
Estimated Cost: $4,000,000
|
| Concrete Street, Street Lights and Water Main Rehab. Project (Town East Blvd.) |
Rehabilitating deteriorated concrete and median pavement, sidewalk and handicapped ramps on Town East Blvd. from E. Emporium Circle to Belt Line Road. Upgrading the median pavement to pavestone or stamped concrete and replacing older street lighting.
Start Date: August 2009 (180 Construction Calendar Days)
Estimated Cost: $2,000,000
|
| Alley, Drainage and Sanitary Sewer Improvements |
Reconstruction of 19 concrete alleys with the replacement of sanitary sewer mains and drainage flumes.
Start Date: June 2009 (360 Construction Calendar Days)
Estimated Cost: $3,000,000
|
| City Hall Expansion, Phase 2 - Utility Improvements |
Relocating 8 inch water and 8 inch sanitary sewer mains to clear and support the future City Hall Expansion Phase 2 Building and reconstructing the street pavement on Municipal Way.
Start Date: February 2010 (75 Construction Calendar Days)
Estimated Cost: $194,000
|
| South Mesquite Creek Sanitary Sewer Trunk Main Replacement, Phase 1 (Wastewater Treatment Plant to Lucas Boulevard) |
Rehabilitation and replacement of sanitary sewer mains, manholes and placement of gabion baskets for channel armoring. A concrete pedestrian path will be constructed adjacent to the City’s Valley Creek Park.
Start Date: August 2009 (240 Construction Calendar Days)
Estimated Cost: $3,500,000
|
| South Mesquite Creek Sanitary Sewer Trunk Main Replacement, Phase 2 (Lucas Boulevard to Pioneer Road) |
Replacement of existing vitrified clay (VCT) sanitary sewer mains with fiberglass sanitary sewer mains.
Start Date: March 2010 (180 Construction Calendar Days)
Estimated Cost: $2,000,000
|
| US 80 at N. Galloway Avenue - Right Turn Lane |
Construction of a dedicated right turn lane on southbound N. Galloway Avenue to west on US 80 service road along with bridge and median modifications. Project is a joint venture with the Texas Department of Transportation Dallas District.
Start Date: Future Development
Estimated Cost: $300,000
|
| The East Corridor |
An
IH 30 / US 80 Design, a Texas Department of Transportation
(TxDOT) project is developing solutions to improve mobility,
safety and travel conditions for these signature east-west
freeways. Designs will initiate with the preparation and
completion of Preliminary Design Schematics and an Environmental
Assessment followed by future final (detailed) design and
project construction.
|
| |
| The East Branch 190 |
An outer loop around Dallas County was first envisioned in 1964. In 1968, the Texas Highway Commission authorized an outer loop around Dallas and designated it as Loop 9. In 1976, a management audit of the State Department of Highway Public Transportation (SDHPT, now TxDOT) indicated a financial shortfall for highway improvements. In 1988, the cities of Garland, Rowlett, Mesquite, and Dallas County sponsored a study to extend SH 190 from SH 78 to IH 20. In 1991, SDHPT commissioned further study of SH 190 from SH 78 to IH 20 and recommended an alignment. In 2000, the North Texas Tollway Authority (NTTA) began an updated/more detailed study that resulted in the alignment of the section from SH 78 to IH 30 that is currently under construction as a tollway. The planning and environmental studies for this the section from IH 30 to IH 20 are ongoing. This section will also be a tollway administered by NTTA. Multiple alignments are currently being evaluated by the Federal Highway Administration with the next round of public hearings expected in early 2009. There is no estimated date for the start of construction.
|